HARTWOOD VILLAGE – AS OF FEBRUARY 2026

  • 3 days ago
  • 1 min read
Hartwood Village
Hartwood Village
HARTWOOD VILLAGE

Percentage Completion:

Land Development: 14.61%

THE FOLLOWING ARE ONGOING WORKS FOR HARTWOOD VILLAGE: – Ongoing Land development works

  • Drainage Works

  • Sewer line Works

  • Electrical UG Duct line

  • Auxiliary UG Duct line

  • Perimeter Fence Construction


– Clubhouse & Bathhouse

– Gateway 1 & 2 / Road & Street Lighting



Other lookahead works:

– Road / Street Lighting (Q3 2026)

– Clubhouse / Guardhouses & Gates Construction (Q4 2026)

– Swimming Pool, Deck, Pumphouse Construction (Q4 2026)

– Central Park Site Devt. (Q3 2026)

– Landscaping Works / Others (Q3 2026)



License to sell:

HLURB LS NO.: DHSUD Region 4A TLS 056 & 072

Project Location: Barangay Malamig, Biñan City, Laguna

Developer: Horizon Land Property Development Corp

Owner: Horizon Land Property Development Corp

Completion Date: June 2026 (Phase 1) January 2027 (Phase 2)





Source: https://federalland.ph/news-and-events/hartwood-village-as-of-feb-2026/